Sabalo Ii Operating, LLC Drilling Permit Activity

Quick answer: Sabalo Ii Operating, LLC has 69 Texas/Oklahoma drilling permits in the last ten years, 34 of them in the last 12 complete months (+25.9% year over year). Its most-permitted county is Andrews (100% of permits) and leading target is Permian Basin (100%).

34
permits, last 12 complete months
+25.9%
vs prior 12 months
69
permits, last 10 years
September 2026
most recent permit month

Permits by year

2024: 5 permits 2024 2025: 32 permits 2025 2026: 27 permits 2026
Sabalo Ii Operating, LLC drilling permits per year (years with 3+ permits) (permits)
Sabalo Ii Operating, LLC drilling permits per year (years with 3+ permits)
Periodpermits
20245
202532
202627
YearPermitsMedian lateral (ft)
2024511,001
20253210,580
20262710,460
Other years combined (3 years)5—

Years with fewer than three permits are combined with at least one other year, so no single year's count is published.

Where it permits

CountyPermitsShare
Andrews (TX)69100%

What it targets

Formation / playPermitsShare
Permian Basin69100%

Permit-to-production timing

Median permit → spud23 days
Median spud → first reported production132 days
Permits older than 12 months that were spudded100%
Spuds older than 12 months reporting production100%
Median lateral, last 24 months vs earlier10,437 ft vs 10,973 ft

Groups with fewer than three permits are folded into "all other". Computed by Valor from public oil and gas data; refreshed weekly. Data as of 2026-11-22.

Using this page

Sabalo Ii Operating, LLC Permits — FAQ

Sabalo Ii Operating, LLC has 69 Texas/Oklahoma drilling permits in the last ten years, 34 of them in the last 12 complete months (+25.9% year over year). Its most-permitted county is Andrews (100% of permits) and leading target is Permian Basin (100%).

Across its permits, the median time from permit to spud is 23 days and from spud to first reported production 132 days. 100% of its permits older than a year have been spudded.

Its median lateral on permits from the last 24 months is 10,437 ft, versus 10,973 ft on earlier permits (-4.9%).

No. Valor publishes permit activity as statistics — counts by year, county and formation groupings of three or more permits, lateral trends and cycle times — rather than individual permit records.